2nd Floor & Amenities

May 26, 2011

Hanover Square is being built in three sections, North, South and Central. The second floor has been cast in the North and South sections. The pool and Jacuzzi areas have been cast.
  • Basement & ground-floor completed throughout
  • Second floor cast in Hanover North and Hanover South
  • Second floor in Hanover Central to be completed soon
  • Third floor preparing to cast in Hanover Square North
  • Interior blockwork commenced
  • Pool & Jacuzzi areas cast