Previous MonthJanuary 2011Next Month


Basement L1 Slab

Jan 3, 2011

The Basement Level 1 Slab has started to pour in some sections. The casting frame for Basement Level 1 is being erected for the remaining sections of the site.
  • Basement Level 1 Slab started casting