SHORING & PILING 40% COMPLETE

Aug 23, 2009

The shoring & piling works are continuing. These along with the initial excavations represent a large portion of the project and more so with Hanover Square given the size of the development with several conjoined plots. Works are proceeding according to the schedule and nearing the half-way mark with over 40% of the shoring and piling in place.
  • More than 40% of the shoring & piling works completed
  • Excavation works commenced
  • Shoring & piling due to complete in September
  • Main excavation due to complete in October