Previous MonthJanuary 2012Next Month


Interior & Exterior Works

Jan 17, 2012

The finishing of the exterior is ongoing with the ornamental cladding and detail works started.

The interior works are progressing well with the MEP works are almost completed and false ceiling suspension works have started in the kitchens and hallways.

  • Exterior work ongoing with ornamental cladding and detail works
  • MEP works near complete
  • False ceiling suspension works started in the kitchen's and hallways