4th Floor Commenced

May 11, 2010

The Third Floor (from the ground) has been cast and will complete tomorrow. Work has already commenced on the Fourth Floor.
  • Basement 2 Floors Complete
  • Ground Floor Complete
  • First Floor / Mezzanine Complete
  • Second Floor Complete
  • Third Floor Completing
  • Fourth Floor Commenced
  • Painting & Plastering of Basement Commenced