5th Floor
Jun 10, 2010 The 5th Floor of the Light is being prepared for casting. Brickwork is continuing on the interior and the exterior and the Lobby is becoming clearly visible in the works and resembling the structure of the interior concept posted in the last update.
Interior Concepts
10 June 2010
The interior design concepts for the Lobby Areas and the Bathrooms have been completed. We have uploaded a gallery of examples of these interior designs for The Light Commercial Tower.
First Floor Brickwork
09 June 2010
The building is now beginning to take shape with the basement levels being prepared and painted. The brickwork is continuing throughout the ground and first floor.
- Building taking shape
- Basement painted
- Brickwork commenced on first floor
|