4th Floor

Feb 7, 2011

The Kensington Manor Project is forming up well with the basement's painted, the 4th floor commenced and the interior work underway.
  • Work started on the 4th Floor
  • Interior brickwork underway
  • Basement Level 1 & 2 painted
  • Utilities being installed

February 2, 2011

The interior concepts have been completed for Kensington Manor. These images give an exciting preview of what to expect in the finished apartments.