PCC Works

Mar 1, 2010

The Main Contractor mobilised on site during February, completing their mobilisation earlier than expected and have commenced immediate work on the waterproofing (PCC & Blockwork) in preparation for the basement. With the ground now compacted, the piled walls of the site and the ground-area will be sealed with cement.
  • Main contractor completed mobilisation during February
  • Compaction completed of the ground area
  • Main Contactor commenced water-proofing of piled walls
  • Blockwork commenced