MAIN CONTRACTOR TO START IN JULY

June 24, 2009

The excavation works are progressing rapidly on Kensington Manor with the site to be handed over to the Main Contractor within the next 3-4 weeks.
  • Site to be handed over to Main Contractor within the next 3-4 weeks
  • Main excavation due to complete within the next 2 weeks
  • Shoring and Piling work 75% complete